Risk assignment
Saturday’s review covers the risk behavioral question and the pre-program planning case the class did not finish.
Nothing on the desk matches that filter.
Playbook
This is the practice desk for the 20 October class, plus the monitoring handout. Behavioral rounds are most of the loop. The rest is how you plan a program: decision rights, a risk score, and a result you keep watching. Open any section below, or use Next at the bottom of each one to go in order. Stories you type stay in this browser only. Download them as Markdown to keep a copy.
Those beats add to about 5:20. The class also wants the whole answer inside 3–5 minutes. Trim the situation before you trim the result. The action is the only long movement, and it is told in “I.”
Saturday’s review covers the risk behavioral question and the pre-program planning case the class did not finish.
Start with Bias for Action, Are Right A Lot, Invent and Simplify, Customer Obsession, and Earn Trust.
Amazon, Uber, Adobe, and some Google teams ask for system design. Start with a system you used today.
Class notes: TPM program planning and behavioral interview prep. Monitoring sections are from the course handout in week-1, not from the live hour. The transcript tool was unavailable, so wording follows the class notes.
From the live class
A project ends. A program keeps the same kind of work moving. Say which one the job description is hiring before you tell a story.
Finite scope, timeline, and budget that produce a unique result.
The same team and the same competencies, repeating similar work. Payments projects live inside a payments program.
Several projects grouped under a larger initiative. The class used a multi-module program as the picture.
The word captives and service firms use. Product companies usually say “program” for that same altitude.
Reporting used to take 40–60% of the day. With AI tools the class put it near 5%. In a product company the TPM is also in the room before the program exists (why and what) and after release (A/B tests, feature iteration).
That was a cross-functional span. The class described the trend as fewer, more senior TPMs owning a program end to end.
The TPM lists mitigations, names an owner for each one, and stays accountable. The TPM is not the decision maker by default.
| Decision | Who calls it |
|---|---|
| Scope change | Product manager |
| Replan inside an approved timeline | TPM |
| Timeline change | Product manager |
Program: direction, quarterly roadmap, goals, stakeholder coordination, impact metrics, and the written artifacts the handout names (HPM, lookback, 1-pager). Technical: domain depth, architecture tradeoffs, requirements broken out of a product initiative, retrospectives. Leadership: trust with senior leaders, negotiation, escalation used on purpose, and the quality of feedback on the team.
From the live class
The hiring manager has to clear you before the loop starts. A bar raiser is not a universal last round.
| Company shape | What changes |
|---|---|
| Amazon, Uber, Adobe | System design is in the loop. |
| System design is now team-dependent. | |
| Intuit | Slide deck plus a case study. |
| Flipkart | Culture, technical, and product rounds. |
| Most other companies | The class put 80–90% of them on technical behavioral questions: influence on a technical decision, judgment under constraints. Domain weighs more at Deloitte, PwC, captives, and service firms. |
Agentic, generative, and robotic AI sit on the application layer on top of those three. A TPM design answer still starts underneath the model.
From the live class
Amazon’s leadership principles are the widest set, so a story that fits them can be retold for Google or Meta. One story per principle. Take the projects from the last five years, and only the ones that were critical to the business.
Leadership-principle fit, and role fit. A clean story that could have been told by an engineer or a product manager still fails a TPM loop if the action is not program judgment.
The class separated L5, L6, and L7 by scale, how many kinds of stakeholders you moved, and business impact. If the job is senior, a single-team launch with no second-order effect is the wrong altitude.
Name the principle you are about to answer before you start. Ask one clarifying question when the prompt is ambiguous. Then talk.
Do not blame a person, a team, or a company. Describe the missing contract, the missing forum, the missing bar.
The class treated SBI, CAR, PAIR, and DICS as the same story in a different frame. Amazon moved from SBI to STAR. For a negative outcome, add STAR+L (what you learned) or STAR+E (what that experience changed in how you run the next program).
Rehearse
Press start and tell a story from the bank. The copper stretch is the action. If you are still setting context when that stretch begins, the story is too long at the front.
Situation: business stakes in one breath. No org chart.
Worked in class
Prompt from class: “Tell me about a time you used a specific metric to identify a need for change.” Primary principle: Insist on the Highest Standards. Also in play: Dive Deep, Invent and Simplify, Deliver Results.
Leave the blanks empty until you have the real figures. Do not memorize invented leakage rates.
Your bank · stays in this browser
Every principle uses the same status: Not started, Draft, or Ready. Draft the five the class named first: Bias for Action, Are Right A Lot, Invent and Simplify, Customer Obsession, and Earn Trust. The word count assumes about 140 spoken words a minute. Land between 3 and 5 minutes. This page does not send your stories anywhere. Download the Markdown file to keep them.
0 ready
From the live class · Saturday’s question
Anything that can knock the program off success: a dependency, a technical limit, unclear requirements, an HR change, legal or compliance. Identification starts at initiation and does not stop.
Walk the path that actually determines the date. Risks that sit off that path get a lower score.
Brainstorm with the people who can see a failure you cannot.
Past projects are a source of risks, not a souvenir.
Description, likelihood, severity, one or more mitigations, an owner per mitigation, an ETA, and a category if it helps you sort. Low = 1, medium = 2, high = 3. Score = likelihood × severity. The class treated 9 as the top of the list.
Pick a cell. Score = likelihood × severity.
You can plan inside an approved date. A date change or a scope change goes to the product manager. You still leave the room with an owner.
Scenario from class
Say it in this order. The class was explicit about the sequence.
Replan, phase the release, or run a parallel path.
Internal staff, a contract team, a vendor, or overtime. Frugality still applies: say what the extra capacity costs.
MVP or descope, Pareto cut, tech debt explicitly after release.
Put the API contract in their hands early, prove it with a POC, escalate through the steering committee.
“I’m assuming this dependency sits on the critical path and that the other team’s roadmap never had this contract, which is a planning gap. The feature misses the date unless we change time, staffing, scope, or the way we integrate. Here are the options and the cost of each. I want the steering committee to pick, and I will publish the decision, the new path, and the single owner for the mitigation the same day. I am not treating this as a failure of that team.”
From the monitoring handout
Monitoring and controlling means tracking progress, finding where the plan has to change, and starting that change. On an agile program the backlog is the control list: a business owner orders it, the team estimates and names technical dependencies, and the next iteration pulls from the top by priority and capacity.
Change requests and defects go into the same backlog as planned work. A separate change queue loses when the rate of change is high. Short iterations then show capacity, change impact, and defect effort, so the next cost, date, and scope estimate comes from real progress.
The handout calls the charts information radiators. They exist to show progress, surface issues, drive a specific improvement, and set expectations. Metrics prove value (on-time delivery, SLA, ROI) and, more usefully, change the next decision, such as slack that is pushing the date.
The handout lists these ten as the starter set. Three of its written formulas are inverted or incomplete. Say the interview form.
| Measure | Handout writes | Say this |
|---|---|---|
| Productivity | Input / output | Output / input. More output for each unit you put in. |
| Gross margin | (Profit − costs) / 100 | (Revenue − cost of goods) / revenue. |
| ROI | (Net benefits / cost) × 100 | Same shape. Benefits can be profit, savings, or more output. Costs include people, training, and overhead. |
| Earned value | % complete / budget at completion | % complete × budget at completion. Also called budgeted cost of work performed. |
| Customer satisfaction | (Survey points / questions) × 100 | Use that index, and name the source: survey, repeat customers, lost customers, or complaints. NPS is the recommend question. |
| Employee satisfaction | The same survey index | Same math. The handout cites Gallup Q12 and notes turnover can cost half to twice a salary. |
| Actual cost | Cost per period × number of periods | The sum of real spend to date. Not the estimate. |
| Cost variance | Budgeted cost of work − actual cost | EV − actual cost. Negative means over budget. |
| Schedule variance | Work performed − work scheduled | EV − planned value. Negative means behind. SPI is EV / planned value, the index form the handout does not write out. |
| Cost performance | EV / actual cost | Same. Above 1 means the spend is producing the value you planned. |
Start from the goal, then the critical success factor, then the measure of that factor. Drop a metric that duplicates another, is not necessary, is subjective, or costs more to collect than it changes.
The handout’s warning: too many similar metrics waste the review, and lowering a target so the chart looks healthy hides the signal. A miss is a reason to find the cause. You are not employed by the dashboard.
Ask two questions before a new metric: will it speed value, and will it raise trust? Use velocity to slice the backlog and forecast a feature. Pay for a higher velocity and the points inflate until the forecast is useless. Operational: lead time, cycle time, burndown. Output: throughput, defect rate, coverage, feature count. Outcome: morale, CSAT or NPS, business value. Scrum treats velocity as the next commitment. Kanban watches lead time, cycle time, the cumulative flow diagram, and a WIP cap so the team swarms a full column.
KPI looks backward at whether the organization is succeeding, and can sit inside a key result. OKR is an objective plus the results that show movement. KPO is the objective itself. A goal is a three- or five-year aspiration and often has no number and no date. MBO is Drucker’s short-term goal-setting between a manager and a team.
A dashboard is a live picture of health so someone can decide. It is widgets, not a second status novel: activity, progress and status, milestones with an owner and dates, a personal to-do, task status, team workload, and where the people are actually allocated.
Gather the sources the team would otherwise hunt for. Show the important number so it can be read quickly. Let the team change the view, because one layout does not fit every program.
One reference stops people drifting off the target. The data sits where the decision is made. A red number is only useful if it becomes an action.
What decision, for whom, how long the read takes, which metrics, which tool supplies them, which number matters most, who owns the follow-up, and what action a miss triggers. The handout’s dashboard KPIs are CPI, alignment to company goals, cycle time, ROI, and how much allotted time becomes output.
From the monitoring handout
A TPM translates in both directions: technical substance for business readers, business stakes for engineering readers. The aim is alignment on scope, milestones, and timeline, plus a cadence that surfaces risks, defects, and mitigations to leadership. After launch, that cadence includes what you did with feedback.
| Choice | Question |
|---|---|
| Format | 1-pager, deck, or email. Match the decision, not your habit. |
| Audience | Internal and external readers need different stakes. |
| Detail | The core team can use the burndown. A VP needs the variance and the ask. |
| Type | Kickoff and a progress update are different documents. |
| Cadence | Core team often, senior leaders less often, both predictable. |
Communication is working when follow-up meetings shrink. Ask the audience. Also use it to ask for help early enough to matter.
Decision makers. Manage expectations closely.
Keep them satisfied. They can still swing the program if they are surprised.
Inform them. They often know the detail that saves you.
Monitor. Do not fill their week.
For each person: what you need from them (a decision, ownership, or feedback), what they actually care about, and the note that follows. There is no single cadence. Fit format, audience, detail, type, and frequency to the program, the size of the room, and the company. The core team hears scope, milestones, and timeline. Leadership hears risks, defects, mitigations, and what you did with feedback after launch. Use the note to ask for help while the help can still change the date.
Put names on a RACI: responsible, accountable, consulted, informed. Leadership in the handout is a style that fits the culture and makes the team feel supported, a look around the whole program for the next risk or the next improvement, and a target the business can see you miss.
Effective communication shows up as fewer follow-up threads asking what the program is doing. Ask the audience whether the note met the need. Anticipate the question and put the answer in the first send.
Stand up a place for defects and enhancement requests. Find the root cause, the severity, and the business impact. Prioritize with a matrix across money, safety, operations, and reputation. Tell the requester yes or no, and when it moves.
Set direction and the strategy in one sentence. Scope the work, publish the quarterly roadmap, and set goals the team can execute. Coordinate the room toward a predictable outcome. Pick the impact metrics. The handout’s formats are an HPM, a lookback, and a 1-pager.
Hold a domain: machine learning, privacy, computer vision, payments, or APIs. See the feature the change creates, and who in the audience it hits. Take a side on the architecture tradeoff, write the recommendation, and break the initiative into technical requirements. Run the retrospective.
Earn enough trust that senior leaders believe you can move people. Use the relationship to extend reach, settle the conflict, and escalate only when the path is blocked. Hold the hard conversation, organize the engineers, and ask for feedback in the moment rather than at the next quarterly review.
Calendar from class
| When | Session |
|---|---|
| Tue 20 Oct | Program planning. This desk. |
| Sat 24 Oct | Assignment review: risk behavioral question, and the planning case left unfinished. |
| Sun 25 Oct | Program execution. |
| Sat 31 Oct | Assignment review. |
| Sun 1 Nov | Monitoring and reporting. Read the handout before you walk in. |
| Diwali week | No Saturday review. Next one is 14–15 Nov. |
Three more behavioral classes sit on the course: introducing frameworks, TPM motivation and core values, and cross-functional collaboration. Sundays are the four-hour class. Saturdays are a case plus three mock questions.